Chinese New Year 2027 falls on 6 February, and factories shut for 2–4 weeks around it — the disruption runs 6–8 weeks. Orders that must ship before the holiday should be confirmed by early December. A proven model like the MT300 — 1.43-inch AMOLED, 440mAh, IP67 — still misses the holiday if ordered in January.
The holidays that stop production
China’s public holidays look short on a calendar, but the effect on a production schedule runs longer: workers travel, suppliers close early, and ports run on skeleton shifts.
| Holiday | When | Effect on orders |
|---|---|---|
| Chinese New Year (Spring Festival) | 6 February 2027 | Factories slow from mid-Jan, close 2–4 weeks |
| Qingming Festival | Early April | 1–3 days; short pause |
| Mid-Autumn Festival | September | 1–3 days; short pause |
| National Day (Golden Week) | 1–7 October | Factories close a week; freight runs hot |
Two holidays dominate the calendar: Chinese New Year and the National Day Golden Week. The short festivals usually cost a few days, not a few weeks — plan a 1–3 day buffer around each.
Chinese New Year in practice
The official Spring Festival break is about a week. The real disruption is six to eight weeks, and it starts long before the holiday: factories wind down from mid-January, and the last dependable ocean sailings leave China between January 15 and 25.
| Phase | Typical window (2027) | What happens |
|---|---|---|
| Order rush | Mid-Dec to mid-Jan | Suppliers rush to finish everything; space tightens, rates climb |
| Wind-down | Jan 9 to Feb 5 | Workers leave in waves; output and inspection quality fall |
| Official holiday | About Feb 5 to 13 | Factories dark, ports on skeleton shifts, banks and customs slow |
| Staggered restart | Feb 13 to Mar 1 | Workers return gradually; 30–40% of migrant workers do not return |
| Full capacity | Early to mid-Mar | Queues clear and the shipping backlog moves |
A factory may also stop accepting new orders weeks before it formally closes, once its pre-holiday schedule is full. Ask every supplier, in writing, for exact closing and reopening dates — they matter more than the public holiday dates.
The weeks on either side of the shutdown are the worst of the year for quality. In the final rush, factories race to clear every order, and in the first weeks back, new workers make new mistakes. Book a pre-shipment inspection for any order shipping close to the holiday — the cheapest protection against a bad shipment landing after the factory has closed.
Work backward from your selling date
Calculate every order date backward from the day the stock must be on sale, subtracting each step in order.
| Step | Typical time |
|---|---|
| Samples and approval | 2–4 weeks |
| Packaging design and printing | 2–4 weeks, parallel with samples |
| Mass production, standard product | 1–3 weeks |
| Mass production, OEM custom | 4–6 weeks after sample approval |
| Sea freight, US West Coast | About 2–3 weeks port to port |
| Sea freight, US East Coast or Europe | About 4–6 weeks port to port |
| Customs, trucking, warehouse check-in | 1–3 weeks, longer at peak |
For Chinese New Year, the backward math lands the purchase-order and deposit deadline between mid-November and early December for a typical reorder. For a new supplier, new tooling, or a large order, order earlier — one guide puts the safe date at late October, 90 to 100 days out, with a 60-to-75-day buffer.
The most common mistake is ordering in December and assuming a January ship date. In practice the pre-holiday schedule is already full, or the order is pushed into the post-holiday backlog until March.
The same math runs the rest of the year. For Q4 sales in the US and Europe, most sea-freight stock should leave China between July and September — a Christmas order placed in October is already late for sea freight and has to fly.
The sales peaks to plan around
Holidays stop production. Sales peaks decide when the stock has to arrive. Plan both calendars together.
| Peak | When | Order deadline (sea freight) |
|---|---|---|
| 11.11 Singles’ Day | 11 Nov | Ship by Sep |
| Black Friday / Cyber Monday | Late Nov | Ship by Sep–Oct |
| Christmas | Dec | Ship by Sep–Oct |
| 12.12 year-end sale | 12 Dec | Ship by Oct |
| Chinese New Year gifting | January–February | Ship before the December rush |
Peak season also raises freight prices and fills vessels, so a shipment that leaves two weeks late can cost more and arrive after the peak. Confirm the sailing date with the forwarder, not just the factory ship date.
What to do in the quiet months
Use the quiet stretches — the weeks after Chinese New Year and the mid-year lull — for samples, new product development, and supplier visits. Test new models when a 2–4 week sample round threatens no sales peak, negotiate next season’s pricing while factories have open capacity, and set the reorder calendar before the busy season starts.
A real example: the MT300
Take a real product: the MT300 smartwatch carries a 1.43-inch AMOLED display at 466×466, a JL7013A chip, Bluetooth LE 5.0, a 440mAh battery, 2-pin magnetic charging, IP67, 11 watch languages, 50 sport modes, and OTA upgrades, at 48×12 mm and 63.5g.

On an MT300 order, the timing writes itself. Order in October and the 1–3 week production run plus 4–6 weeks of sea freight to Europe still lands the stock before Christmas. Order the same watch in January and the factory is already winding down — the stock ships in March, after the gifting season it was bought for. The product did not change. The calendar did.
See our Smartwatch Sourcing Guide, lead time guide, and quotation comparison guide. Browse our products page.
Frequently Asked Questions
When should I place my order before Chinese New Year 2027?
Get the purchase order and deposit in by mid-November to early December for a typical reorder, so production finishes at least two to three weeks before the factory closes. For a new supplier, new tooling, or a large order, order earlier — late October is the safe date in one guide, with a 60-to-75-day inventory buffer. Ask the factory in writing for its exact closing date.
How long do factories really close for Chinese New Year?
The official public holiday is about a week, but export factories effectively shut for 2–4 weeks, and the total disruption runs 6–8 weeks: a mid-December to mid-January order rush, a wind-down from early January, the holiday, and a staggered restart into early March. Up to 30–40% of migrant workers do not return, so the first weeks back run slower and with higher defect risk.
Which other Chinese holidays affect electronics orders?
The National Day Golden Week (1–7 October) is the second big one — factories slow or close for a week and freight runs hot around it. The short festivals — Qingming, Labour Day, Dragon Boat, Mid-Autumn — usually cost 1–3 days each. Add a small buffer around each and confirm the factory’s schedule in writing.