Chinese New Year 2027 falls on 6 February. Factories start winding down two to three weeks before it, close for two to four weeks, and need three to four weeks after the holiday to reach full capacity again. About six weeks disappear from mid-January to early March. Order by mid-December and the goods ship before the shutdown.
The shutdown is six weeks, not one
The official Spring Festival holiday lasts about a week; the factory shutdown is much longer. Production starts slowing three to four weeks before the holiday as workers leave for their home provinces, and some factories stop taking new orders four to six weeks out. Assembly lines halt about two weeks before the date.
After the holiday, production does not switch back on in a day. Some workers never return, so the factory rehires and retrains, and reaches full capacity three to four weeks later. One logistics estimate puts it plainly: 80–90% of manufacturers stop production entirely, with shutdowns of 10–21 days and full recovery taking up to four weeks. All told, the disruption runs six to eight weeks.
Watch quality at two points: the last week before the holiday, when the line is racing the plan, and the first weeks after, when new staff are working it. Our delivery factors guide lists the other things that move a date.
The 2027 calendar: count backwards from 6 February
| Milestone | 2027 timing | What to do |
|---|---|---|
| Confirm orders | Late November to early December | Lock the order and the deposit; ask for closure dates and the last ship date in writing |
| Last realistic order | Mid-December | After this, the goods will most likely ship after the holiday |
| Last ocean shipments | Late December to early January | For CNY 2026 the published cut-offs were 10–18 January for FCL and 5–12 January for LCL; CNY 2027 falls 11 days earlier |
| Last air shipments | Early January | For CNY 2026 the published air cut-off was 1–10 February; for 2027, plan on the last week of January |
| Wind-down | Mid-January | Lines slow, workers leave, new orders stop; ship finished goods |
| Shutdown | 6 February, plus 2–4 weeks | Factories closed; no new orders are processed |
| Ramp-up | Late February to early March | New staff, retraining, slow return to full output |
Plan backwards from the factory’s real stop date, not the public holiday. Your last realistic pre-holiday shipment is set by when the factory can finish and pack, not when it can start. Split large orders when the calendar is tight: ship the fast movers before the holiday and the balance after, when freight rates ease.
Other holidays that break a plan
National Day runs 1–7 October, and factories close for the week — exactly when fourth-quarter production should be finishing. Build it into the plan in advance instead of discovering it in September.
The fourth quarter itself is a deadline, not a holiday. Black Friday falls on 27 November 2026, a peak that can be around sixty percent of annual revenue for toy retail. Orders for that season go in August to September: sea freight to the US needs an order by early September, and after that you are paying air rates. The same backward count applies — from the shelf date to the order date, not from the order date to hope.
Labour Day and the Dragon Boat Festival close factories for a few days each. They rarely break a plan on their own, but they sit inside production windows and eat days a tight schedule does not have. Put them on one calendar with your supplier and forwarder, and confirm the dates in writing every year.
What to ask your supplier in December
Closure dates. Ask for the factory’s exact stop and restart dates, when they stop taking new orders, and the last cargo-ready date. Put them on one calendar shared with your team and the forwarder.
Inspection timing. Confirm production milestones and inspections 10–14 days earlier than usual, because line speeds drop as workers head home. A pre-shipment inspection booked for the last week before the holiday catches the rushed batch; one booked after the restart catches the new-staff batch.
Buffer stock. Hold four to six weeks of safety stock for CNY-exposed SKUs, worked out per SKU from daily sales and total lead time — production, inspection, transport, transit, clearance, receiving — not the supplier’s quoted production days alone.
Split and mode. Ask which SKUs can split into a pre-holiday and a post-holiday batch, and what the freight options cost. If a must-arrive date cannot be met by ocean, book deferred air or premium ocean with a guaranteed window. See our production schedule guide for how factory slots work, and our sourcing calendar for the full year of dates.
Featured model: the GT100PRO
The GT100PRO smartwatch is a good model to run these questions against: a Realtek 8763EWE chip, a 1.46-inch full-touch display at 360×360, Bluetooth 4.0/5.2, a 360mAh watch battery with 30mAh earbuds docked in the case, IP67 waterproofing, and 128MB of flash memory, at $32.50–$36.50. Every number there comes from the product page. Earbud playtime is not stated — get it in writing before you quote it.

The point is not the watch: ask the December questions on a model like this one, and the holiday shutdown stops being a surprise.
Frequently Asked Questions
When should I place my order to beat Chinese New Year 2027?
By mid-December. Factories wind down two to three weeks before the 6 February holiday and stop taking new orders weeks before that, so an order placed after 1 January will most likely ship in March. Confirm the order in late November or early December, and get the factory’s closure dates and last ship date in writing. The goods have to be finished and packed before the lines stop, not merely started — a production start date in January is not a ship date. If the order cannot ship before the holiday, plan for the March ramp-up instead of hoping for February.
Can I place an order during Chinese New Year?
No. Factories are generally closed, and suppliers will not process new orders during the holiday. The closure lasts two to four weeks, and full capacity takes another three to four weeks to return, so the earliest realistic ship date for a new order is March. Use the break to plan the spring buy instead: confirm the assortment, the quantities, and the buffer stock, so the order goes in the day the factory reopens. Your supplier’s sales contact may still answer messages, but the line will not run — a reply is not production.
How much buffer stock should I hold for Chinese New Year?
Four to six weeks of cover for CNY-exposed SKUs, worked out per SKU from average daily sales and total lead time — production plus inspection, inland transport, transit, clearance, and receiving. The buffer covers both the shutdown and the slow post-holiday ramp-up, when new staff are still being trained and lines run below full speed. Size it per SKU, not as one number for the whole order: fast movers need more cover than slow lines, and stock sitting on a shelf costs money too.